McCrossan: Planning system has ground to a halt
SDLP Opposition AERA Spokesperson Daniel McCrossan MLA has said that delays have caused the planning system to grind to a halt.
He was speaking after an Assembly Question confirmed 576 planning consultations are awaiting a response, including 526 statutory and 50 non-statutory consultations.
Currently, 364 statutory planning consultation that have exceeded the statutory consultation period.
Mr McCrossan has also uncovered that there are currently 40 full-time Northern Ireland Environment Agency (NIEA) staff, eight on temporary or agency contracts and 23 vacancies.


The West Tyrone MLA said: “It is clear that with nearly 600 planning consultations awaiting a response and over half of them having exceeded the normal period that our planning system has effectively ground to a halt. This means that a wide variety of projects, from much needed homes, to the expansion of businesses and community and leisure facilities are being subjected to undue delays.
“The impact of this will be felt across our society, it means more people on housing waiting lists, jobs and investment being missed out on and communities not having their basic needs met. These delays will mean projects get more expensive, leaving some developers to think twice about proceeding. It’s clear that the current system isn’t working.
“These delays cannot be helped by the fact that the NIEA is currently down a third of its staff. These applications will never be processed in a timely manner with the NIEA functioning so far from full capacity and until this is addressed delays will continue and get worse.
“It’s clear that the process around statutory consultees needs serious reform if progress is to be made and I will be directly challenging the DAERA Minister on these delays and to bring forward solutions to clear this backlog and get our planning system back on its feet.”